Highway signage gantries |K10 Kloten-Bülach-Nord Highway| 2016

06.07.2017 - 13:30

Project description

Supply and assembly of finished and flag signage gantries.

Technical features

Total weight of steel 30 tons
Width: up to 32.5 m

Height: up to 7.5 m

Technical description

Within the renovation of the K10 highway between Kloten and Bülach, a total of 3 finished gantries and two flag gantries and their platforms were subcontracted. 

During the restoration of the lane towards Eglisau, two finished gantries were installed. Exceptionally one of these gantries is 32.5 m wide. Thus, even the section of the welded pipes is huge (600 x 700 mm). 

The gantries were assembled closing the highway during the night between the 28th to the 29th of June.

Client

Kanton Zürich, Baudirektion, Tiefbauamt

Engineer

WSP W. Schefer + Partner Ingenieurbüro AG, Hinwil

Supervision of construction

WSP W. Schefer + Partner Ingenieurbüro AG, Hinwil