Highway signage props | Piottino | 2007

.

Portali di sostegno segnaletica autostradale | Piottino | 2007

Client

Dipartimento del territorio

Engineering firm

IM Maggia Engineering AG

Description

Reorganization of the vertical signage and renovation of the side-roads of A2 highway in Piottino area.

Technical features

285 tons

Distributed elements:

11 double-props (filling the two directions)

8 props on flyover

37 signal crossbeams in the tunnel

Technical description

Vertical signage gantries composed of various dimensions hot-rolled steel tubular.

The gantries non passable are provided with a simple framework and the gantries passable are composed of Vierendeel beams. 

The surface treatment was obtained by hot-dip galvanization.